Auditor's Office Fort Worth, Texas, Nov 7th 1902
To the Hon. Mayor and City Council
Gentlemen:
We, your Commitee on Finance recommend. That the Mayor and City Secretary be authorized and instructed to execute the Citys notes, in favor of the Neptune Meter Co. for the balance due them amounting to the sum of $237508 in accordance with contract.
Wm G Newby } Finance JF Henderson } Commitee
3
JOHN B. HAWLEY. CONSULTING ENGINEER. MEMBER AMERICAN SOCIETY CIVIL ENGINEERS. CITY ENGINEER, FORT WORTH.
FORT WORTH, TEXAS. Nov. 3rd. 1902.
Hon. the Mayor and City Council, Fort Worth, Texas.
Gentlemen:- Below please find final estimate of work done and material furnished by Brown and Dabney contractor Main Street paving from a line 50 feet South of the South line of Ninth Street northward.
Intersection East side 9th.St. | as per est. 12-7-00. | 186 2/3 Sq.Y |
---|---|---|
" " " 8th,St. | " " | 186 2/3 " |
" " " 7th.St. | " 1-4-01. | 130 " |
" " " 6th.St. | " " | 186 2/3 " |
" " " 5th.St. | " " | 186 2/3 " |
" " " 4th.St | " 2-1-03. | 186 2/3 " |
" " " 3rd.St. | " 3-1-01, | 186 2/3 |
" " " 2nd.St. | " 4-5-01. | 186 2/3 " |
" West " 9th.St. | " " | 186 2/3 |
" " " 8th.St. | " " | 186 2/3 |
" " " 6th.St. | " 5-28-01. | 160 " |
" " " 5th. St. | " " | 186 2/3 " |
" " " 7th.St. | " 7-5-01. | 130 " |
" East " 1st.St. | " " | 186 2/3 " |
" West " 4th.St. | " 11-15-01. | 182 " |
" " " 3rd.St. | " " | 182 " |
" " " 2nd. St. | " 12-6-01, | 182 " |
" " " 1st.St. | " " | 182 " |
Error in last four intersections each 4 2/3 S.Y. | 18 2/3 " | |
Intersection East & West sides of alley between 2st and | ||
Weatherford Sts. | as per est. of 3-21-02. | 142 2/9 " |
Intersections Houston Street North 50 ft.East side of 5th. | ||
and South 10ft. East side of 4th. Sts. | as per est. of 5-28-01. | 186 2/3 |
3548 8/9 " |
3548 8/9 Sq. Yds. @ $1.85 | $6565.44 |
---|---|
Less Houston street as above 186 2/3 S.Y. @ $1.85 | 345.33 |
6220.11 |
Less intersections West and East sides of 9th.,8th.,7th., | |
---|---|
6th, and 5th. on which bond of $250.00 was filed | |
Nov. 1st 1901. 1726 2/3 S.Y. @ $1.85 | 3194.22 |
3025.77 | |
Less 10% retained | 302.58 |
2723.20 | |
Less previous payments | 2692.12 |
Amount Due | 31.08 |
John B. Hawley Respectfully,
Addition extensions Correct JJ Nunnally City Auditor
5
JOHN B. HAWLEY. CONSULTING ENGINEER. MEMBER AMERICAN SOCIETY CIVIL ENGINEERS. CITY ENGINEER, FORT WORTH.
FORT WORTH, TEXAS. Nov.7th. 1902.
Hon. the Mayor and City Council, Fort Worth, Texas.
Gentlemen:- Attached hereto please find Estimate No. 13 of work done and material furnished by L.S.Leversedge and Co. contractors on the Jennings Avenue Viaduct.
Respectfully, John B. Hawley City Engineer