Below please find Estimate No.8, of materials furnished and work done by
The McQuatters Machine & Plumbing Co., on the New Sewerage System.
-- | -- | -- |
---|---|---|
18,344 feet 15 inch Sewer, laid, | @$1.10 | $20,178.40 |
3,857 " 12 " " " | 0.70 | 2,699.90 |
7,555 " 10 " " " | 0.50 | 3,777.50 |
25,373 " 8 " " " | 0.40 | 10,149.20 |
91,707 " 6 " " " | 0.30 | 27,512.10 |
2,026 " 15 " Pipe, delivered, | 0.55 | 1,114.30 |
489 " 12 " " " | 0.34 | 166.26 |
1,408 " 10 " " " | 0.24 | 337.92 |
2,652 " 8 " " " | 0.18 | 477.36 |
22,483 " 6 " " " | 0.18 | 2,922.79 |
5412 cu. yds. Rock Excavation | 2.50 | 13,530.00 |
75.415 tons Cast Iron Pipe in place | 46.40 | 3,499.25 |
19.825 M. Lumber left in trench, | 36.40 | 722.63 |
450 cu. yds. Concrete in place | 6.60 | 2,970.00 |
8 Manholes, | 35.00 | 280.00 |
14 Lamphole, | 3.50 | 49.00 |
Extra haul, 15" Pipe, to "Armstrong Route" | 40.30 | |
$90,426.91 | ||
Less 15 per cent retained, | 13,564.04 | |
$76,862.87 | ||
Estimate No. 1, In cash | 9307.50 | |
" " 2 (In Cash | 6106.55 | |
" " 3, (In cash, ) | 9585.95 | |
( In Certificates ) | 3780.34 | |
" " 4, In Certificates | 8549.70 | |
" " 5, " In Certificates, | 11,853.07 | |
" " 6, In Certificates, | 10,512.36 | |
" " 7, In Certificates, | 10,504.02 | |
$70,199.49 | 70,199.49 | |
Balance due (In Certificates) | $6,663.38 |
To which I certify,
John B Hawley