Here you can see all page revisions and compare the changes have been made in each revision. Left column shows the page title and transcription in the selected revision, right column shows what have been changed. Unchanged text is highlighted in white, deleted text is highlighted in red, and inserted text is highlighted in green color.

3 revisions
lkarnatz at Dec 18, 2017 09:17 PM

25

THIRTEENTH DISTRICT
PORTLAND, OREGON Dec 17 187???

???man Light House Board,
Washington, D.C.
Sir:
I have the honor to make the following Report of Operations for the month of October 187???
Cape Foulweather Lt Station, Ogn.
Received 1 cargo of Materials. Hauled materials, including Sand Water to L.H. Site. Roof, Cornice & ceiling of Oil-House completed - Iron Work fitted & placed, to the top of 4th stairs. Tower walls completed to top of necking??? course. 2 Coats Cement Wash put on Tower Wall so??? - as completed. Commenced 1st coat of paint on Oil House.
Probable Operations in November.
Receive 1 cargo materials. Complete carpenter work & painting. Finish Tower walls. Get casting from Portland to replacea landing which does not fit.
Cape Flattery Lt. Station, W.L.
Sent machinist. who put the Fog Signal apparatus into complete order, fitted Boiler for use of salt water & instructed Keepers (none of whom has had experience in running a steam engine) in the use of salt & fresh water in boiler. Supplied station with Stove, Engine, Clock, & complete set of tools needed for Signal; delivered 10 cords of wood for Fog Signal.

25

THIRTEENTH DISTRICT
PORTLAND, OREGON Dec 17 18???

???man Light House Board,
Washington, D.D.
Sir:
I have the honor to make the following Report of Operations for the month of October 18???
Cape Foulweather Lt Station, Ogn
Received 1 cargo of materials. Hauled materials including sand water to L.H. ???. Roof Cornice & ceiling of Oil-House completed- Iron Work lifted & placed, to the top of 4th stairs. Tower walls completed top of necking course. 2 Coats cement wash put on Tower Wall so - as completed. Commenced 1st coat of paint on Oil House.
Probable Operations in November.
Receive 1 cargo materials. Complete carpenter work & painting. Finish Tower walls. Get casting from Portland to replace ???ding which does not fit.
Cape Flattery Lt. Station, W.L.
??? machinist. who put the fog signal apparatus into complete order, fitted boiler for use of salt water & instructed Keepers (none of whom has had experience in running a ??? engine) in the use of salt & fresh water in boiler. Supplied station with ???, Engine, Clock, & complete set of tools needed for Signal; ??? 10 cords of wood for Fog Signal. 594