or the abandonment of the work by the employees, through
no default of the contractors, then the time herein
fixed for the completion of the work shall be extended for
a period of time equal to the time lost by reason
of any or all of the causes aforesaid, but no such
allowance shall be made unless a claim therefor
is presented in writing to the building Committee, and
the Architect within 24 hours of the occurrence of such
delay. The duration of such extension shall be certified by the
building Committee, and there architect.
Article - 8 - :
The owner agrees to provide all labor
and material not included in this contract in
such manner as not to delay the material progress
of the work, and in the event of failure so to do thereby
causing loss to the contractor, agrees that it will
reimburse the contractor for such loss; and the
[inserted] Contract for
New Library [end inserted] contractor agrees that if he shall delay the material
progress of the work, so as to cause any damage for
which the owner shall become liable as above stated
then he shall make good to the owner any such
damage.
Article - 9 - :
It is hereby mutally agreed between
the parties hereto that the sum to be paid by the owner
to the contractor for said work and material
shall be - $32. 311. 17., subject to additions and deductions as
here in [inserted] before [end inserted] provided, and that such sum shall be paid
in current funds by the owners to the contractor
in installments as follows:
Said payments to be made
from the time to time in accordance with the
monthly estimate to be approved by the Building
Committee and said architect - In accordance
with the above provisions payments shall be
made on all suitable [?materials?] delivered to
the building site less 50 per cent, provided
always that all material delivered on the