52
Facsimile
Transcription
Status: Complete
JOHN B. HAWLEY,
CONSULTING ENGINEER,
MEMBER AMERICAN SOCIETY CIVIL ENGINEERS.
MEMBER ENGINEERING ASSOCIATION OF THE SOUTH.
MEMBER TEXAS ASSOCIATION CIVIL ENGINEERS.
FORT WORTH, TEXAS, May 7th, 1906. 1905
Hon., The Mayor and City Council,
Fort Worth, Texas.
Gentlemen:-
Below please find estimate No. 7 of materials furnished and work done by
The McQuatter Machine & Plumbing Co., on the New Sewage System.
16,344 feet | 15 inch Sewer, laid, @ | $1.10 | $17,978.40 | |
2,957 " | 12 " " " | 0.70 | 2,069.90 | |
6,428 " | 10 " " " | 0.50 | 3,214.00 | |
20,778 " | 8 " " " | 0.40 | 8,311.20 | |
86,691 " | 6 " " " | 0.30 | 26,007.30 | |
3,923 " | 15 " Pipe, delivered, | 0.55 | 2,257.65 | |
1,056 " | 12 " " " | 0.34 | 359.04 | |
2,542 " | 10 " " " | 0.24 | 600.08 | |
7,247 " | 8 " " " | 0.18 | 1,304.46 | |
8,249 " | 6 " " " | 0.13 | 1,072.37 | |
4,912 cu. yds. | Rock Excavation, | 2.50 | 12,280.00 | |
73.88 tons | Cast Iron Pipe, | 46.40 | 3,468.03 | |
15.673 M. | Lumber left in trench, | 36.40 | 570.50 | |
414 cu. yds. | Concrete in place, | 6.60 | 2,732.40 | |
8 | Manholes, | 35.00 | 280.00 | |
12 | Lampholes, | 3.50 | 42.00 | |
Extra Haul, | 15" pipe, to "Armstrong route" | 40.30 | ||
$82,587.63 | ||||
Less 15 per cent retained, | 12,388.14 | |||
$70,199.49 | ||||
Estimate No. 1, | In Cash, | $9,307.50 | ||
" " 2, | In Cash, | 6,106.55 | ||
" " 3, | (In Cash) | 9,585.95 | ||
(In Notes) | 3,780.34 | |||
" " 4, | In Notes, | 8,549.70 | ||
" " 5, | In Notes, | 11,853.07 | ||
" " 6, | In Notes, | 10,512.36 | ||
$59,695.47 | 59,695.47 | |||
Balance due, ( In Notes ) | $10,504.02 |
John B. Hawley
City Engineer
by W. S. Cunningham