Final estiate of work done and material furnished at 5th. Ward
School house, to date, John Bardon, Contractor. Nov. 20th. 1905.


-- -- --
General contract $24560.00
Extras, 40 yds concrete footings @ $5 200.00
" 2 vent flues @ $80., heating plant 160.00
" Lowering arear walls 10.00
" 2 scuttles, 2 hatches and 2 ladders 20.00
Total $24950.00
Credits.
Apr. 8th. Cash 1674.50
May 20th. " 369.75
June 17th. " 2275.45
July 22nd. " 5163.15
Aug. 19th. " 2469.68
Sept. 16th. " 528.00
Oct. 2nd. " 8114.85
20595.38
By reservation made for items yet to be
completed, flashing to caps to columns,
columns to be matched to one color. 75.00
20670.38
Balance due $4279.62