136
fully completed by the date above mentioned
the contractor shall forfeit and pay or cause to
be paid to the owner the sum of fifteen dollars
per day for each and every day thereafter the
said work remains in an unfinished condition,
for an as liquidated damages , and to be deducted
from any payments due or to become due
to said contractor.
Art-7- Should the contractor be
obstructed or delayed in the prosecution or
completion of his work by any act neglect,
delay, or default of the owner or architect, or
of any other contractor employed by the owner on the
work , or by any damages which may happen by
fire, lightning, earth quake, or cyclone, or the
abandonment of the work by the employes, through
no default of the contractor, then the time herein
fixed for the completion of the work shall be extended
for a period of time equal to the time lost by reason
of any or all of the causes aforesaid, but no set
allowance shall be made unless a [?claim?] therefor is
presented in writing to the Architect within twenty four
hours of the occurrence of such delay. The duration of
such extension shall be certified by the Architect.
Art-8- The owner agrees to provide
all labor and material not included in this contract
in such manner as not to delay the material
progress of the work, and in event of failure so to do
thereby causing loss to the contractor agrees that he
will reimburse the contractor for such loss; and
the contractor agrees that if he shall delay the
material progress of the work so as to cause any
damage for which the owner shall become liable
as above stated then he shall make good to the
owner any such damages.
Art-9- It is hereby mutually
agreed between the parties hereto that the
sum to be paid by the owner to the contractor for said